Skip to main content
Jyot Enterprise

Engineering · Precision Engineering

Arva Industries - Rebuilding a fixture nobody had drawings for

An undocumented assembly fixture was reverse engineered, redesigned and validated - removing 22% of cycle time and two-thirds of rejections.

Client overview

Arva Industries operates in precision engineering. The engagement ran across our Engineering practice.

Problem statement

Arva's main assembly cell depended on a fixture built in-house fourteen years earlier. Tolerances had drifted, final inspection rejection sat near 9%, and throughput could not be raised. No drawings existed and the engineer who built it had retired.

Research

  • The fixture was 3D scanned and critical interfaces verified on a CMM to establish actual versus intended geometry.
  • Three months of inspection data was analysed to correlate rejection modes with specific fixture features rather than operator variation.
  • Time study across two shifts isolated where the 42-second cycle was actually consumed - 11 seconds sat in clamping and repositioning.
  • Mating component drawings were reviewed to infer the original design intent and the tolerances that mattered.

Planning and approach

  • A ground-up redesign in SolidWorks with a revised clamping scheme replacing four manual clamps with two pneumatic units.
  • FEA validation of the base structure under clamping load, which identified the deflection responsible for most tolerance drift.
  • Correct GD&T applied against measured process capability rather than inherited nominal tolerances.
  • The surrounding cell layout was reworked to remove two material-handling movements per cycle.

Execution

Weeks 1-2 · Capture

Scanning, CMM verification and inspection-data analysis completed on site.

Weeks 3-5 · Design

Concept selection, detailed modelling, FEA and design review with the plant team.

Weeks 6-9 · Build

Fabrication supervised at a partner shop with in-process inspection at each stage.

Weeks 10-11 · Commission

Installation, first-article inspection, operator training and documentation handover.

Timeline

  1. Weeks 1-2

    Reverse engineering and data analysis

  2. Weeks 3-5

    Design and simulation

  3. Weeks 6-9

    Fabrication and inspection

  4. Weeks 10-11

    Commissioning and handover

  5. Month 12

    Post-implementation audit of cycle time and reject rate

Results

Return on the engagement.

Reduced rejection alone paid for the engagement in seven months. The throughput gain removed the need for a second shift that had been planned for the following quarter.

2.9x

Return in year one

22%

Cycle-time reduction

-67%

Final inspection rejects

9 → 3%

Rejection rate

“We expected a new fixture. We got a documented, revision-controlled design with an inspection plan that our quality team now uses as a template. The documentation alone was worth the engagement.”
Pranav DesaiPlant Head · Arva IndustriesEngineering

Conclusion

What we would tell a similar business.

The gain here came from sequencing - fixing the measurable constraint first, then building around it. If your business shows the same symptoms Arva Industries did, the diagnosis usually takes one conversation and a look at ninety days of data.

Next step

Tell us the problem. We will tell you what it takes.

A 30-minute consultation with the practice lead who would actually run your mandate - no sales layer in between.